Carrier - Fibre - Connectivity - Tampnet - Norfest
Providing greater capacity, more redundancy, and direct routes along the coast of Norway and into Sweden, the unique and reliable routes generated through the system will provide access to the most in-demand locations.
This project has been commissioned to enhance routes connecting the UK to Europe via the Nordics, with over 700 km of brand-new fibre!
NORFEST has 10 landing points that have been strategically selected to provide connectivity to the most sought-after PoPs and carbon-neutral data centres in the Nordics, with maximum flexibility to ensure robust, reliable, and scalable services to meet future demands. In keeping with Tampnet's stringent quality and performance standards, the new infrastructure will provide reliable, low-latency, high-capacity connectivity to vital Data Centres and PoPs, with unique routing options to enhance your critical operations.
Read the full whitepaper here.
24. June 2023:
Cable loadout was carried out at Nexans' Rognan Cable Plant Pier. The process was smooth and completed well ahead of schedule!

27. June 2023:
Our first branch was laid from the Egersund shore, heading out to sea for connection to the Western trunk which will be installed in July.

19. July 2023:
The Edda Fjord began installation of the Stavanger Branch from Green Mountain Data Center. Over the next few days, the team will move northwest through the channel and then continue south to Kristiansand.
26. August 2023:
The Norfest Western Trunk installation scope continues, with the Kristiansand branch floated into Nodeviga over the weekend and tied back to our landing station. Even the local dolphins were curious!

31. August 2023:
The Lista branch was successfully installed from Skagerrak to Husebysanden. This was the Final step for the Western Branch installation. The Eddafjord will now head back north to close out some branching scopes before returning to base for a short project. In October, we will begin load-out of the Norfest Eastern Trunk and branches.
6. September 2023:
Egersund - Cable Landing Station (CLS) Huts are installed with solar panels and the connections are completed. Throughout the design and installation of this project, the team focused on creating the most sustainable solutions at each stage. The CLS huts are a great tangible example of this.

16. October 2023:
The Eddafjord started laying the Eastern Trunk of the Norfest Cable. Despite wild weather conditions sweeping through the North Sea, the project maintained momentum. Cecon's installation crew worked tirelessly to ensure safety integrity of the cable during the lay process.
10. November 2023:
The cable lay continues as the Eddafjord travels towards the Oslo Fjord. The next stops are Moss and Drøbak where the fjord narrows and strong surges can be experienced.

15. November 2023:
The Norfest Trunk is almost complete, with the Edda Fjord arriving in Oslo this afternoon!
.png?width=613&height=681&name=MicrosoftTeams-image%20(38).png)

27. November 2023
Eddafjord arrives in Larvik to complete tie back to the trunk cable. Only 2 more branches to go!
30. November 2023:
The Eddafjord travels to Tromøy to complete tie back on the Arendal branch.
6. December 2023:
Norfest safely landed in Capri, Sweden.